Construction Started Today February 10, 2010 Thanks for a little dry weather, a group of high
qualified servant volunteers. MMAP’ers And ROAM’ers These are Christian RV’ers
who travel around building the Kingdom with hammers,
saws, brushes and shovels. Makes me want to shout, Hallelujah! |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
After
the Snow Construction
begins again With
cement footers poured February
16, 2010 |
|
|
|
|
|
|
|
Feb
17, 2010 Pier
and Beam Foundation
is underway. |
|
|
|
|
|
|
|
Feb
18, 2010 More
foundation work and a picture of the MMAP’ers at work Friday
and Saturday We
are driving to: I-beams |
|
|
|
|
|
|
|
Feb
19, 2010 Trips
were made More
blocks laid I-beams
here ready for Monday |
|
|
|
|
|
|
|
|
|
|
|
|
Monday, February 22, 2010 We are almost
ready to start building with lumber. Oops! The delivery
truck is too long to make the turn into either one of our Driveways. So we have to
wait for a fork-lift. It is nearly 6 p.m. The Fork-lift
and another truck arrived. I will take pictures of the lumber near the
Construction site tomorrow. It is getting dark. |
|
|
|
|
|
|
Tuesday,
Feb 23, 20100 Cement
poured in the blocks Steal
Beams in place Lumber Ready
to use |
|
|
|
|
|
|
|
|
|
|
|
Wednesday February
24, 2010 Today
was time For Wood,
Glue, Nails |
|
Hammers and |
|
|
Saws |
|